Poland is preparing one of its largest motorway-capacity upgrades as traffic on the A2 between Warsaw and Łódź approaches 100,000 vehicles per day. The 92-kilometre project will add lanes across most of the route and is designed to keep one of Poland’s busiest transport corridors moving as demand continues to grow.
A Motorway Built for Expansion
The A2 between Warsaw and Łódź opened to traffic in 2012, but its capacity is already coming under pressure. According to Poland’s latest traffic measurements, daily traffic ranges from almost 60,000 vehicles near Łódź to nearly 100,000 closer to Warsaw.
The solution is a major widening project covering 92 kilometres. Additional lanes will be built along 89 kilometres of the route, while work on the remaining three kilometres will focus on the Łódź Północ interchange.
The expansion has been planned into the motorway’s original design. Space was reserved in the central median for additional lanes, while bridges and other structures were designed to accommodate future widening.
Once the project is completed, the section between Łódź Północ and Pruszków will have three lanes in each direction. Between Pruszków and Konotopa, the motorway will have four lanes in each direction.
Work Moves Into Its Next Phase
Poland has divided the investment into four construction sections. By September, contracts for three of them had been signed, with the combined project value estimated at almost PLN 1.5 billion.
The first contract, covering the 17.2-kilometre Grodzisk Mazowiecki–Konotopa section, was signed in June. A second contract for 21.8 kilometres between Łowicz and the Łódź–Mazowieckie voivodeship border followed in August. In September, GDDKiA signed the third contract, covering another 25.5 kilometres between the voivodeship border and Grodzisk Mazowiecki.
The remaining 27.9-kilometre section between Łódź Północ and Łowicz is the final contract still to be completed.
Preparatory works are already changing traffic organisation around several major interchanges, including Opacz, Warszawa Zachód, Wiskitki and Mszczonów Północ. The changes are intended to improve alternative routes and maintain traffic flow while the motorway is being widened.
During the main works, Poland plans to keep two lanes available in each direction. Authorities are also planning average-speed enforcement on parts of the construction corridor to improve road safety.
Preparing for Poland’s Next Traffic Increase
The A2 is more than a connection between two major Polish cities. It is part of an important east-west transport corridor serving passenger traffic, logistics and freight.
The motorway’s rapid increase in traffic demonstrates a wider challenge facing European road infrastructure: major motorways can reach capacity much sooner than originally expected when economic activity, vehicle ownership and freight demand continue to grow.
Poland is also using the project to test a different approach to motorway infrastructure. The expanded A2 is planned to become an energy-self-sufficient motorway section, with renewable energy installations supplying road infrastructure such as lighting and weather stations. Energy storage is also being considered as part of the system.
The entire A2 expansion between Łódź and Warsaw is currently scheduled for completion by 2028.
The project therefore represents more than simply adding another lane. It is an attempt to redesign one of Poland’s busiest motorway corridors for a significantly higher level of traffic while keeping the existing route operational throughout construction.