Construction of one of Poland’s most ambitious road bridges has reached a major milestone. Engineers have completed the concrete deck of one carriageway of viaduct ES-26 on the S19 expressway between Babica and Jawornik.
The national road authority, GDDKiA, announced the development on 27 October 2026. The viaduct is being built across challenging, hilly terrain in southeastern Poland, where deep valleys make conventional construction methods difficult.
The structure will be 1,082 metres long, with piers reaching up to 80 metres above the ground. Once completed, it will be the highest viaduct in Poland.
Building a bridge above a deep valley
The ES-26 viaduct consists of two parallel structures carrying traffic in opposite directions. It is located between Żarnowa and Godowa, where the landscape presents significant engineering and logistical challenges.
The height of the piers makes it impractical to support the entire bridge deck with conventional scaffolding from the ground. Instead, engineers are using a cantilever construction method.
Under this approach, concrete sections are built progressively outwards from the bridge piers. Special formwork equipment supports each new segment as the structure extends over the valley.
Sections are constructed in a balanced sequence on either side of the piers. This allows the bridge deck to grow without requiring extensive temporary supports below it.
The method is particularly useful in difficult terrain, where deep valleys, steep slopes and limited access can complicate construction.
Concrete transport is a major logistical challenge
One of the main challenges during construction of the first bridge deck was transporting concrete to considerable heights.
The work requires a steady supply of concrete and careful coordination between delivery, pumping and construction operations. According to GDDKiA, completing the first deck will also make the next stage easier.
The completed structure will provide a route for transporting concrete and equipment to the second viaduct. This is expected to simplify logistics as work progresses on the carriageway in the opposite direction.
The next stage will involve constructing the starting segments of the second deck and continuing the concrete works.
S19 is part of a wider transport corridor
The viaduct forms part of the 11.6-kilometre S19 Babica–Jawornik section in southeastern Poland. The project is a significant part of the country’s wider expressway development and the international Via Carpatia route, which is intended to improve north–south road connections in Central and Eastern Europe.
According to the road authority, overall construction progress on the Babica–Jawornik section has exceeded 80%. Bridge works are more than 90% complete, while road construction is approaching 70%.
The project has received EU funding through Poland’s European Funds for Infrastructure, Climate and Environment programme, known as FEnIKS.
Once finished, the section will provide a modern expressway through a demanding landscape. The ES-26 viaduct is one of its most technically challenging structures, demonstrating how specialised bridge-building methods can help deliver road infrastructure in areas where terrain makes construction particularly complex.